2021 Projects


Delameter Road

Project Limits: Mileposts 0.90 to 2.33Delameter PH1.jpg

Federal Classification: Rural Major Collector (07)

Project Description: Reconstruct roadway to include 12-foot travel lanes with widened shoulders. Includes horizontal/vertical alignment improvements.

Basis for Project: Narrow roadway with little shoulder room. Poor visibility due to horizontal/vertical alignment.

Funding: Project funding includes $1,174,500 Federal Grants, $747,000 State Grants, and $2,472,500 County Funds for a total of $4,394,000.

Schedule: Construction complete.

Contact: Roger Maurer, Project Manager / Engineer, (360) 577-3030



Spencer Creek Road Slide Repair 

Project Limits: Milepost 1.52 to 1.56 Spencer Crk.jpg 

Federal Classification: Rural Local Access (09)

Project Description: Repair the existing roadway by installing a rock buttress and repaving the roadway surface. The existing guardrail will be reviewed and upgraded as needed.

Basis for Project: Existing roadway and guardrail were damaged during the 2015 flood event. The damage has created the need for narrower lanes as the roadway continues to settle.

Funding: Project funding consists of $420,000 of Local Road Funds.

Schedule: Construction completed.

Contact: Chris Andrews, Project Engineer / Manager, (360) 577 - 3030



Curve Signs

Project Limits: Various locations throughout the County. CurveSigns 

Federal Classification: Various Classifications

Project Description: This project will install curve warning signs on roadways throughout the County.  These signs will include warning signs that include advisory speeds and chevrons directing drivers around curves.

Basis for Project: Currently there is an emphasis on accident prevention by completion of low cost projects.  Curve warning signs have been shown to decrease runoff the road accidents which is a leading type of accident on rural roads within the County.

Funding: This project is receiving funding from the Federal Highway Safety Improvement Program (HSIP).  This program funds 90% of the project engineering and 100% of the construction costs.  The federal funding is $409,000 with a local Road Fund match of $1,000.

Schedule: Construction completed.

Contact: Chris Andrews, Project Manager/Engineer, (360) 577 - 3030


Wren Loop Road and White Road Culvert Replacements

Project Limits: Wren Loop Road Milepost 0.28 to 0.31 Wren-White Road Culvert.jpg

White Road Milepost 0.04 to 0.07

Federal Classification: Rural Local Access (09)

Project Description: The failed 36" diameter culvert and two smaller culverts on Wren Loop Road will be replaced with and 18-foot span culvert. The White road culverts will be replaced with a 14-foot span culvert. The project will also include development of a simulated stream bottom through the new culverts, guardrail installation and roadway repairs.

Basis for Project: The 26-inch diameter culvert on Wren Loop Road has failed and the roadway is closed. The culverts on both roadways are undersized and either have failed or are approaching failure. The culverts operate as a system and all of the culverts need to be replaces for the system to function properly. The culverts are also a barrier to fish passage and can become clogged with debris allowing water to build up on the upstream face of the roadway.

Funding: Project funding includes $521,000 Federal Grants, $87,000 State Grants and $102,000 Local Road Funds for a total of $710,000.

Schedule: Construction completed.

Contact: Roger Maurer, Project Manager / Engineer, (360) 577 -3030


Coyote Lane Baxter Creek Culvert 

 Project Limits: Milepost 0.11 to 0.21 Coyote Lane Baxter Creek.jpg 

Federal Classification: Rural Local Access (09) 

Project Description: This project will replace an existing undersized 7.00’ diameter culvert with a bridge. 

Basis for Project:  The existing culvert is a fish barrier that also has the potential to plug and flood the roadway.

Funding: Project funding includes $2,096,500 State Grants and $374,500 Local Road Funds for a total of $2,471,000. 

Schedule: Construction completed.

Contact: Roger Maurer, Project Engineer / Manager, (360) 577 - 3030