2018 Projects
Rose Valley Road Embankment Repair
Project Limits: Milepost 0.21 to 0.34
Federal Classification: Rural Major Collector (07)
Project Description: Stabilize the embankment in the vicinity of existing washout.
Basis for Project: During the December 2015 storm event water washed over the roadway and the embankment severely eroding the embankment and creating a steep slope that without stabilization will undermine the roadway.
Funding: Project funding includes $2227,400 Federal Grant, $0 State Grant and $52,600 County Funds for a total of $280,000.
Schedule: Construction is expected to occur in 2018.
Contact: Roger Maurer, Project Manager / Engineer (360) 577 - 3030
________________________________________________________________________________________________
Little Kalama River Road Drainage Improvement
Project Limits: Milepost 6.77
Federal Classification: Rural Minor Collector (08)
Project Description: Replace 32" by 60" squash pipe culvert with a 12' concrete "bottomless" culvert. The new culvert will allow for improved fish passage and prevent future clogging. The project is at 90% design and is permitted.
Basis for Project: Existing cross-culvert is undersized and failing.
Funding: Project funding includes $476,300 Federal Grants, $79,400 State Grants and $84,300 County Funds for a total of $640,000.
Schedule: Construction is expected to occur in 2018.
Contact: Roger Maurer, Project Manage / Engineer, (360) 577 – 3030.
________________________________________________________________________________________________
Bodine Road Slide Repair
Project Limits: Milepost 2.01 to 2.04
Federal Classification: Rural Local Access (09)
Project Description: Relocate section of road to avoid existing landslide area.
Basis for Project: Earth movement is damaging the roadway shoulder with the potential for movement of the entire roadway.
Funding: Project funding includes $180,000 Federal Grants, $30,000 State Grants and $42,000 County Funds for a total of $252,000.
Schedule: Construction is expected to occur in 2018.
Contact: Roger Maurer, Project Manager / Engineer, (360) 577 – 3030.
______________________________________________________________________________________________
Rose Valley Road Retaining Wall
Project Limits: Milepost 0.45 to 0.46
Federal Classification: Rural Major Collector (07)
Project Description: Replaced the existing retaining wall.
Basis for Project: High flows during the December 2015 storm event scoured out material within and beneath the existing crib wall.
Funding: Project funding includes $0 Federal Grants, $0 State Grants, and $321,000 County Funds for a total of $321,000.
Schedule: Construction is expected to occur in 2018.
Contact: Roger Maurer, Project Manager / Engineer, (360) 577 -3030.
_______________________________________________________________________________________
Dike Road Reconstruction
Project Limits: Milepost 1.7 to 3.05
Federal Classification: Rural Local Access (09)
Project Description: Reconstruct the roadway section to improve the structural strength of the roadway
Basis for Project: Increased truck traffic has caused severe damage to the roadway because this roadway does not have an adequate roadway section to support frequent fully loaded trucks.
Funding: Project funding includes $0 Federal Grants, $0 State Grants, and $1,000,000 County Funds for a total of $1,000,000.
Schedule: Construction is expected in 2018.
Contact: Roger Maurer, Project Manager / Engineer, (360) 577 – 3030.