4. Structural Plans to include:
a. Foundation Plan
b. Floor Framing Plan(s)
c. Roof Framing Plan
d. Truss Information (see item II, C)
e. Cross Sections as necessary
f. Framing Details
g. Structural Material Specifications
5. HVAC/Plumbing *
a. Show HVAC equipment
and plumbing fixtures
b. Smoke detector locations
6. Electrical Plan *
a. Outlets, Fixtures,
Switches, Smoke Detectors, and Service Panels.
B. Calculations (2) sets of:
1. Structural Calculations
2. Energy Calculations and Forms
C. Other Documents
1. Soils Report or Geologic Study
II. Information
to be Included on Documents
A. Information on plans:
1. Name, title,
registration (address and phone number) of designer.
2. Address of property.
3. Name, address, phone number of the property owner
4. Cover Sheet Information
a. Applicable codes and editions
b. Description and type of all work
c. Occupancy and type of construction
d. Gross area, by floor(s) and building height
e. Index of drawing information
B. (#)Details included in plans:
1. Windows: head, jamb and
sill heights
2. Exterior doors: head, jamb and threshold
3. Flashing: vertical junctures of materials
4. Fireplace - masonry or prefabricated fireplace
5. Footing, piers and grade beams
6. Roof: eaves, overhangs, rakes and gables
7. Floor changes (i.e., wood to concrete)
8. Handrail(s) and guardrail(s) with support
9. Structural wall sections (details at foundation, floor and
roof levels).
10. Stairway rise and run, framing, attachment and
dimensions.
11. Connections (post & beam, etc.)
12. Any special framing details
C. (#)Prefabricated trusses: provide
(Item 1or 2)
1. Submit following:
a. Roof Framing Plan with Truss I.D. No. and
Manufacturer's Name
b. Detail of all Truss Splices, Connections and Plate
Sizes
c. Show all Trusses including Gable Bracing and Bridge
d. Review by Individual Responsible for Design
2. Provide Single Line
Truss Diagram with All Vertical and Lateral Loads including Bearing
Points Shown with Reference of Framing Plan
D. Separate Plans &Permits Required
for the Following Types of Work **
1. Automatic Fire
Sprinkler Systems
2. Accessory Structures Proposed on the Plot Plan
3. Structure Demolition
(*) Plans
can be combined for simple buildings, if clarity is maintained.
(**) This is
not a complete list of all required submittals, your project may require
additional
information after plan review.